New Construction On 9th Street In Lake Oswego Oregon

April 13, 2021

During the testing phase of the new pump station a discrepancy was discovered with the pump motors. New motors will have to be manufactured to rectify the discrepancy. The estimated timeline for delivery of replacement motors is approximately 6 to 10 weeks. For the most part the project will be put on hold until the project receives the replacement motors and can resume testing. Some minor landscaping work will continue on the site. If you have any questions feel free to contact David Kudna Project Manager at 503.635.5299.

March 18, 2020

Nighttime Water Main Shutdown: Week of March 23

During the week of March 23, the water main that serves residents and business in the FAN neighborhood will shut down between the hours of 10 p.m. to 5 a.m. for construction. The service interruption should be limited to one night during this week. All properties that may be impacted will receive a flier announcing the day and time of the water main shutdown.

 Water will not be available during this time, so residents are encouraged to store extra water if needed. When water service resumes, please run the cold water for several minutes to flush the lines. Thank you for your patience and cooperation.

Project Overview

The City is planning improvements to its water system at the 10th Street Reservoir and Pump Station property located at the corner of 10th Street and C Avenue. This project includes removal of the water tank and replacement of the existing pump station.

Anticipated Project Timeline

Construction: February 2020 – Fall 2020

September 5, 2019 - Preliminary Work Begins Week of Sept. 9

Preliminary work begins the week of September 9 for exploratory digging for utilities as part of the project.

9th Street, between B Avenue and C Avenue, and C Avenue, between 9th Street and Country Club Road will close to all through traffic from 7 am - 4 pm for approximately one week. Local access will be maintained for residents within the closure area.

This work is preparing the area for improvements to the water system. Major construction work is expected to start in late 2019 or early 2020. More information will be available as the project moves forward.

April 25, 2019 - Project Open House on May 13

Come along to the project Open House to learn about upgrades to the water system and give your input on key project details!

Monday, May 13, 2019
6:30pm-8pm

New Thought Center for Spiritual Living
1040 C Ave, Lake Oswego, OR 97034

January 2, 2019 – Survey and Field Work at the 10th Street Reservoir and Pump Station Site

Neighbors may see design survey and geotechnical drilling at and near the reservoir site beginning this month. You may also notice tags placed on some trees along the street and at the reservoir property. These tags are used to identify the trees and should remain until the project is completed. These tags do not mean the trees are planned to be trimmed or removed. Thank you for your assistance.

January 18, 2019 – Tree Survey Beginning

Neighbors may see a consulting arborist conducting a tree survey of all existing trees within right-of-way within the project area and on the reservoir property.

March 20, 2020 - Nighttime Water Main Shutdown: Week of March 23 (Not Related to COVID-19)

During the week of March 23, the water main that serves residents and business in the FAN neighborhood will shut down between the hours of 10 p.m. to 5 a.m. for construction. The service interruption should be limited to one night during this week.  All properties that may be impacted will receive a flier announcing the day and time of the water main shutdown.

Water will not be available during this time, so residents are encouraged to store extra water if needed.  When water service resumes, please run the cold water for several minutes to flush the lines.  Thank you for your patience and cooperation.

This shutdown is not related to the current outbreak of COVID-19. Our drinking water is safe. We will continue to deliver safe drinking water to your tap throughout the COVID-19 emergency.

Project Overview
The City is planning improvements to its water system at the 10th Street Reservoir and Pump Station property located at the corner of 10th Street and C Avenue. This project includes removal of the water tank and replacement of the existing pump station.

Anticipated Project Timeline
Construction: February 2020 – Fall 2020

Questions?
David Kudna, Project Manager
Phone: 503-534-5299

Source: https://www.ci.oswego.or.us/engineering/10th-street-water-system-upgrade-project